Pembroke Schools Biomass

A  5 MMBTUH Messersmith combuster/boiler with single cyclone emission control 1,100sf new, 1,000sf renovated lab requiring excavation and shoring for equipment clearances.  Congested urban site required double-sided drive-in woodchip storage bin with full length clear span truck bridge Hydronic service to two schools Pembroke Academy and Three Rivers Elementary School.

Location: Pembroke, NH
Project Cost: $3,000,000
Gross Square Feet:
1,100 sf New Construction
1,000 sf Renovation
Start/Completion Date: 2010
Construction Manager/General Contractor: Eckman Construction
Major Consultants:
Civil – Nobis
Structural – Steffensen
Mechanical – GWR
Electrical – Swiftcurrent
Woodchip Heating Consultant – Better World Energy

Project Images